In an important milestone the last jackets for the 950 MW Moray East offshore wind farm were safely loaded onto the heavy lift vessel at Rig Metals LLC (part of Lamprell) in Dubai ready for their onward journey to Europe, under the management of DEME Offshore.
In another key milestone and despite the many challenges brought about by the coronavirus pandemic, DEME Offshore successfully installed the third and final offshore OTM substation on schedule last weekend.
Bart De Poorter – General Manager DEME Offshore commented: “Managing to perform the seamless installation of the third offshore substation and keeping foundation production firmly on schedule are both something we can be proud of given the unprecedented challenges we have faced. This is only possible by meticulous management, thorough preparations and by working closely with our customer and partners.”